Construction Update

Construction Update - Main focus is getting ready for winter and completing exterior areas.

  • The east addition's structural brick will be finished next week. This addition will house the theater's main electrical panels and other crucial utilities. It will also be home to a dedicated piano storage room and fire exit for the east side of the theater.

  • The west addition's exterior framing is approximately 90% complete. This extensive addition to the theater will house a full-size loading dock, green room, star dressing rooms, and men's/women's dressing rooms on the 1st floor. The 2nd floor will consist of a large flexible space that can be used for classes, rehearsals, meetings, and additional room for theater operations if needed.

  • A brick veneer will soon be added to the west addition, which will enclose the space in preparation for winter

  • The marquee and blade sign fabrication is approximately 35% complete. This portion is being built off-site and will be delivered/installed in early 2018.

Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square