Construction Update

Construction Update - Interior work is expected to ramp-up soon.

  • Roof installation on the main theater building is 75% complete.

  • Masonry block and brick is currently being installed on the West Addition. Priority has been placed on finishing this aspect prior to the winter months.

  • Masonry restoration has been completed on the original structure, with a final inspection left to perform.

  • Drywall installation has just started with approximately 5% complete.

  • Plaster repair on the main theater ceiling is underway.

  • 85% of door frames have been installed.

  • The 2nd floor bar is beginning to take shape, as drywall and other materials are added.