Construction Update - Heavy Lifting up on the Roof
December 1, 2017
New HVAC units have been installed on multiple roof areas.
A large crane was required to lift these heavy units.
All partition framing is 95% complete.
Roof installation/repair is 95% complete.
All concrete floors have been poured throughout the new additions.
The Auditorium floor concrete is scheduled to be poured within the next 4-6 weeks.
Data/Telecom/CCTV/Security vendors will start in the next 1-2 weeks.
Plaster repair in the auditorium is almost complete.
Drywall installation is beginning in some areas of the original theater.