Construction Update - Heavy Lifting up on the Roof

New HVAC units have been installed on multiple roof areas.

  • A large crane was required to lift these heavy units.

  • All partition framing is 95% complete.

  • Roof installation/repair is 95% complete.

  • All concrete floors have been poured throughout the new additions.

  • The Auditorium floor concrete is scheduled to be poured within the next 4-6 weeks.

  • Data/Telecom/CCTV/Security vendors will start in the next 1-2 weeks.

  • Plaster repair in the auditorium is almost complete.

  • Drywall installation is beginning in some areas of the original theater.

Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
DardMasks.png

LEAVE A LASTING MARK IN OUR HISTORIC THEATER!

>LEARN MORE<

Email Us: Link
Contact:  304.624.1500
  • Facebook - White Circle
  • Twitter - White Circle
  • Instagram

Renovation and restoration of the Robinson Grand Performing Arts Center is public-private partnership of the City of Clarksburgthe North Central West Virginia region, and The Cultural Foundation of Harrison County.

©2020 ROBINSON GRAND. 

  • Facebook - White Circle
  • Twitter - White Circle
  • YouTube - White Circle