Construction Update - Progress Continues in Many Areas
East Addition masonry has been completed.
Partition framing throughout the facility is almost complete.
Light fixture installation in the Ballroom and Performance Hall is approximately 40% complete.
Two of four masonry sculptures on the West Addition have been installed.
Door frame installation throughout the facility is approximately 97% complete.
Drywall installation and plaster repair is in progress.
Catwalks have been installed in the stage house.
Structural improvements are being made to the roof trussing for support of stage lighting and audio systems.
Elevator components are being installed.
Rooftop HVAC units have been installed.
Electrical, Data, Voice and CCTV wiring is being installed.
The Performance Hall floor is scheduled to be poured in the next two weeks.