Construction Update - Work Moves On, Despite Cold Temperatures
Light fixture installation in the Ballroom and Performance Hall is 55% complete.
Interior framing on the first floor of the West Addition is 98% complete.
West wall masonry of the West Addition is complete.
Installation of the (4) masonry sculptures on the West Addition is complete.
Roof installation on the auditorium is complete.
Drywall installation throughout the facility is 40% complete.
Structural improvements to the roof truss system in the auditorium is complete.
The loading dock CMU installation is approximately 65% complete.
Tile installation in the 1st floor restrooms has started.
Installation of (2) elevators is ongoing.
Plumbing, HVAC, Electrical, and sprinkler line installation will continue.