Construction Update - Interior Work Ramps Up
Partition framing in the theater building and restrooms/concession area is complete.
Light fixture installation in the ballroom and auditorium is approximately 85% complete.
Interior framing on the first floor of the west addition is almost complete.
Door frame installation throughout the facility is complete.
Drywall installation is 65% complete.
Installation of wall tiles in the first floor restrooms is almost complete.
Installation of floor tiles in the concession area is almost complete.
Installation of (2) elevators is ongoing.
Plumbing, HVAC, Electrical, and sprinkler line installation will continue.