Construction Update - Interior Work Continues with Some New Exterior Additions
Installation of steel structure for front blade sign is approximately 25% complete.
Drywall installation throughout the facility is 80% complete.
Installation of wall and floor tiles in the first and second floor bathrooms is approximately 95% complete.
The stage walls and fly loft/ceiling grid is approximately 80% painted, including the grid iron and roof structure.
The loading dock garage door has been installed.
Electrical, mechanical, and security equipment is arriving/installed daily.
The historic film projectors have been removed from the projection booth in preparation for a new high definition projector and new spotlights. The historic projectors will be on display for all patrons to view.
Drywall is currently being installed on the Ballroom's iconic arched ceiling.
Poster display windows are beginning to take shape along West Pike Street.