Construction Update - Major Progress Can be Seen as Spring Weather Arrives
Ballroom window installation is complete and 80% have been painted.
Installation of ticket booth windows is 85% complete.
Drywall installation is 90% complete in the theater and concession areas.
Installation of wall tiles in the first and second floor bathrooms is 99% complete.
Paint application on basement walls is 95% complete.
Balcony aisle handrails are 90% complete.
Framing of upper balcony box seats is 90% complete.
Paint application in ballroom is 80% complete.
Paint application in Bar area is 65% complete.
Steel Structure for blade sign has been painted.
Stage rigging line set installation is 45% complete.
Elevator installation is ongoing.
Marquee elements will be arriving throughout the next month.